AIDC Special Act to Take Effect on March 10 Next Year
Implementation procedures are taking shape for the 'Special Act on the Promotion of the AI Data Center Industry,' set to take effect on March 10 next year to foster the growth of AI data centers. The Ministry of Science and ICT announced on the 20th that it has drafted the enforcement decree and enforcement rules (subordinate regulations stipulating the actual execution of the law) required for implementation, and will open them for public comment (a process for gathering public opinion) until the 30th of next month. The draft includes the scope of recognition for AI data centers, business reporting procedures, a method for processing multiple permits at once, special exemptions from power impact assessments, and criteria for designating special zones. This will enable operators to identify applicable benefits and administrative procedures in advance.
As computing demand surges with the spread of AI services, securing large-scale data centers has emerged as a task that determines national AI competitiveness. However, since these facilities require vast amounts of power, cooling equipment, and telecommunications networks, site acquisition, power supply, and various permits have been pointed to as obstacles to business development.
The government has established criteria for determining which AIDCs qualify for support under the special act. Eligible facilities are those equipped with a certain level of AI accelerators, secured with power and cooling infrastructure, and with a design power ratio of 1.5 or below. Colocation facilities that provide racks for AI computing without directly owning data centers are also included.
Reporting procedures have also been divided into stages. A construction report must be filed before construction begins, and an operation report must be filed no later than 30 days before operations start. If changes arise, an amendment report can be submitted within 30 days.
Behind the introduction of the reporting system lies the problem of phantom operators. Concerns were raised that some might file construction reports without breaking ground, pre-empting special benefits such as exemptions from power grid impact assessments. Accordingly, operators must set and report a planned construction start date within one year of filing their report.
According to the draft enforcement decree, the special act takes effect on March 10 next year, and AI data centers newly built, expanded, or converted in non-metropolitan areas with contracted power of 50MW or less are exempt from power grid impact assessments. This is a measure to disperse investment concentrated in the capital region to provincial areas. For gigawatt-scale megaprojects and projects eligible for consolidated permit processing, a fast track will expedite assessments, and for facilities located in special zones, the government will consult with the Ministry of Climate, Energy and Environment to devise measures exempting them from non-technical assessments.
Building regulations will also be improved. Considering that AIDCs have few resident staff and visiting vehicles, the mandatory requirement for attached parking lots has been lowered by 20% from existing standards, and a legal basis has been created allowing local governments to further relax this by up to 50% through ordinances. Requirements for EV-only parking spaces and charging facilities will likewise be set by municipal and provincial ordinances within a range of 1-5% of total parking spaces.
The AIDC special zone system is also being made concrete. When a local government applies, the central government will review it within 90 days and decide on designation after deliberation and resolution by the AI Committee. The scope of special zone support has been expanded beyond power and water supply facilities to include transportation infrastructure such as roads and bridges, heat supply facilities, energy storage systems, waste heat recycling facilities, ultra-high-speed communications networks, security and disaster response facilities, and resident coexistence infrastructure. The enforcement rules include the scope of eligible equipment and ancillary facilities, along with 10 types of administrative forms. The government also plans to prepare regional coexistence guidelines, including a process for gathering residents' opinions, by the first half of next year.
The Ministry of Science and ICT plans to gather industry feedback during the public comment period and, after legislative review and other procedures, enforce the special act and its subordinate legislation simultaneously on March 10 next year. The full text of the draft is available on the ministry's website, and a public hearing will be held on the 9th of next month at Nuri Dream Square in Mapo District, Seoul.